Reconstruction of three intersections for the City of Longview, WA.

Completion date: October 2009

Looking South on 15th Avenue

This job took place at three major intersections along 15th Avenue in Longview, WA (Fir, Delaware and Douglas).  Work included removal of existing pavement, sub grade excavation, repairs to sanitary and storm sewer, installing new base rock re-paving with concrete and asphalt pavement, and re-striping.  Work in high traffic areas was completed under tight time constraints at night and on weekends.  

Our contract was completed on time even with the unexpected addition of some necessary storm line work discovered in the middle of a Friday night!  

Partnering with us on tis job were: Hildebrand Concrete, Karvonen Paving and Carlson Testing, Mill Plain Electric and Specialized Pavement Marking.